Analysis Of Time And Cost Performance With Earned Value Method In Lecture Building Project Development Of Nutrition Department At East Kalimantan Health Polytechnic

Khoirul, Huda and Mulyadi, Lalu and Santoso, Agus (2018) Analysis Of Time And Cost Performance With Earned Value Method In Lecture Building Project Development Of Nutrition Department At East Kalimantan Health Polytechnic. INTERNATIONAL JOURNAL OF SCIENTIFIC & TECHNOLOGY RESEARCH, 7 (2). ISSN 2277-8616 56

[img] Text
Analysis-Of-Time-And-Cost-Performance-With-Earned-Value-Method-In-Lecture-Building-Project-Development-Of-Nutrition-Department-At-East-Kalimantan-Health-Polytechnic.pdf

Download (463kB)
[img] Text (Ujiplagiasi)
15. Lamp. III.A.3c-6.pdf

Download (562kB)
[img] Text (Pereview)
16.pdf

Download (386kB)

Abstract

The research is started at the beginning of Lecture Building Project Development of Nutrition Department at Health Polytechnic of East Kalimantan Starting Week 1 (21 June 2016) to 24 week (13 December 2016); cost performance at Lecture Building Development Project of Nutrition st th th Department at Health Polytechnic of East Kalimantan until the 24 week is good and efficient based on the value of ACWP = IDR 9.744.811.962,07, th which is smaller than the value of BCWS = IDR 21.583.712.069,60 and the value of BCWP = IDR 13.728.265.040,05 as well as the value of the Cost Performance Index (CPI) = 1,208. For project time performance, it has a delay. It can be seen from the condition of the 24 week of the schedule th performance index (SPI) value which is = 0,858 1, the value of Schedule variance (SV) = IDR. -1.953.203.330,25. The time for the completion of the rest project is 5 weeks, so the total time for project completion is 31 weeks from the initial schedule of 26 weeks. While the remaining costs needed to complete the work (ETC) after the 24th week is = 4.841.426.269,65 or the cost needed to complete 100% of the work (EAC) is = IDR 11.361.245.034,44.

Item Type: Article
Uncontrolled Keywords: Terms: cost, earned value concept, schedule, variance.
Subjects: Engineering > Architectural Engineering
Institut Teknologi Nasional Malang > Fakultas Teknologi Industri > Architectural Engineering
Divisions: Fakultas teknik Sipil dan Perencanaan > Teknik Arsitektur S1
Depositing User: Mr Sayekti Aditya Endra
Date Deposited: 23 May 2019 02:19
Last Modified: 06 Jul 2019 03:25
URI: http://eprints.itn.ac.id/id/eprint/3535

Actions (login required)

View Item View Item